What’s your status? Forgetting to set a status date (flaw 7)

Hey there,

Here is the second addition to my series on incorrect use of Microsoft Project stand alone version. It started as a list with 5 most common mistakes people use during there scheduling experiences, however some people have suggested additional flaws, this flaw was also hinted by Swagato Bandyopadhyay, thanks again, and hope you like this post as well. Continue reading What’s your status? Forgetting to set a status date (flaw 7)

Using predecessors in Summary tasks (flaw 6)

Hey People,

Let me start by thanking you for some of the great responses I got on my serries on incorrect way’s to use Microsoft Project stand alone version. Most people agreed on the flaws I noted in the series of blogs, and some had additions to the flaws.

I have picked a number of additional flaws, that I believe need to be discussed. Today I’ll post my thoughts on linking summary tasks. This flaw was suggested by Swagato Bandyopadhyay, thank you, I hope you like what I did with your suggestion. Continue reading Using predecessors in Summary tasks (flaw 6)

Lost in translation – a Microsoft horror story

This is a post to vent some frustration, it will not give you new insights on MS Project or Project Server. However, if you are Dutch like me, it might make you smile. If you’re here to learn something try my series  on incorrect use of the product.

— Update August 2017 —

I’m happy to say that I now am part of the “Microsoft Office Language Quality” A Linked In group created with the help of Microsoft to support better language support trough out the world.
Continue reading Lost in translation – a Microsoft horror story

Not using the baseline functionality (flaw 5)

Hi there,

This is my last post in my series about incorrect way’s to use Microsoft Project stand alone version. In it I have discussed some of the common flaws people run into when using the Project application. This post will be about the baseline functionality, it is often forgotten or ignored by project managers. I will be talking about why you should want to have a baseline in your project. Again this is a very theoretical subject and you should always check with your company if there are any policies regarding baselining a project. Continue reading Not using the baseline functionality (flaw 5)

Too much detail in the schedule (flaw 4)

Hi there,

This is the fourth post in my series on incorrect use of Microsoft Project stand alone version. In my last post I talked about the lack of a Work Breakdown Structure, and this post will continue on that path. Please feel free to give your own insight on the subject because it is highly theoretical. Here goes!
Continue reading Too much detail in the schedule (flaw 4)

Lack of structure (Work Breakdown Structure) (flaw 3)

Hi there,

This is the third post in my series on incorrect use of Microsoft Project stand alone version. I hope you can relate to the situations I described so far and I hope you have learned some nice insights on the workings of MS Project. This post will be about structuring your project to an agreeable level. This structure is called a Work Breakdown Structure or WBS for short. Continue reading Lack of structure (Work Breakdown Structure) (flaw 3)