Tag: Project management
Book review: Dynamic Scheduling with MS Project 2010
The Dynamic Scheduling books (2003, 2007 and 2013 also available) are a great way to get to know Microsoft Project and learn some of the key features that help you build a schedule that last the whole project life cycle. As far as I know there isn’t a 2013 version yet.
In my work as a consultant I have seen a lot of people use date related planning, the Dynamic Scheduling method helps define a better way to building a project plan. The book is nicely arranged and has some good best practices from building Work Breakdown Structures (WBS) to Earned Value (EV) calculations.
The book comes with a nice set of Web Added Value (WAV) downloads and will be a great way to learn for Microsoft certification Exam 70-178: Microsoft Project 2010, Managing Projects. Grab your own copy of the book by going to this link.
I would give this book a score of 4 out of 5 stars.
Book reviews on Project management and MS Project (server)
Hi readers,
As a consultant I try to read and know as much as possible about the subjects I’m considered to be an expert in. Apart from blogs and Microsoft TechNet there is a whole universe of project (management) literature out there to suite just that need. This is why I started doing book reviews!
Continue reading Book reviews on Project management and MS Project (server)
Book review: De Projectsaboteur (The Project saboteur)
I’m sad to say the book is currently only available in Dutch and I don’t know if there is an English translation on the way. However: If you are an international project manager and need to manage a project in The Netherlands, please read this book. This little book is a real gem. It’s to the point and a nice introduction in the subtle sabotaging ways of Dutch project members. And a great way to learn the Dutch language. Continue reading Book review: De Projectsaboteur (The Project saboteur)
Building a visual custom field for late progress in MS Project professional
I got a respons on one of my earlier posts.
I have a task with a start date in the past, completion is 0% and the “i” column doesn’t show that calendars.
The “i” column or indicator column doesn’t show the information described in the comment. Here is the complete list of the indicators it does show. Any new indicators you need to build yourself using custom fields and graphical indicators. I’ll build the custom field and indicator using the new MS Project professional 2013 but it will work on just about any other version. Continue reading Building a visual custom field for late progress in MS Project professional
About baselines
Hi there,
In a recent post I mentioned incorrect use, or no use at all of the baseline functionality in Ms Project. In this post I would like to dive deeper into baselines from an application perspective. Continue reading About baselines
Not using the baseline functionality (flaw 5)
Hi there,
This is my last post in my series about incorrect way’s to use Microsoft Project stand alone version. In it I have discussed some of the common flaws people run into when using the Project application. This post will be about the baseline functionality, it is often forgotten or ignored by project managers. I will be talking about why you should want to have a baseline in your project. Again this is a very theoretical subject and you should always check with your company if there are any policies regarding baselining a project. Continue reading Not using the baseline functionality (flaw 5)