Building a visual custom field for late progress in MS Project professional

I got a respons on one of my earlier posts.

I have a task with a start date in the past, completion is 0% and the “i” column doesn’t show that calendars.

The “i” column or indicator column doesn’t show the information described in the comment. Here is the complete list of the indicators it does show. Any new indicators you need to build yourself using custom fields and graphical indicators. I’ll build the custom field and indicator using the new MS Project professional 2013 but it will work on just about any other version. Continue reading Building a visual custom field for late progress in MS Project professional